A submittal and buyout checklist for Divisions 21–26

Check equipment tags, electrical coordination, deviations, quote exclusions and closeout documents before you issue a package.

Standardizing intake and release gates across Divisions 21, 22, 23, and 26 prevents Revise-and-Resubmit cycles and post-award change orders.

Schedule & tag completeness

Confirm every tag on FP-601, P-601, M-601, and E-601 maps to an active, orderable manufacturer SKU and current cut-sheet revision.

Electrical & enclosure coordination

Verify voltage, phase, FLA, MCA, MOP breaker size, kAIC fault rating, and NEMA indoor/outdoor enclosure class across trades.

Substitutions & AIA deviation log

Separate exact Basis-of-Design matches from CSI 01 25 00 Approved Equals and list every accepted deviation on the AIA A201-2017 § 3.12.8 cover table.

Quote scope-exclusion reconciliation

Verify roof curbs, vibration isolation, factory disconnects, controls, freight, lead time, and Division 01 78 46 attic stock across all distributor bids.

BABA, LEED v5 & closeout O&M

Attach signed domestic-content certificates, Environmental Product Declarations (kgCO2e), installed serial numbers, and warranty start dates.