Approved as noted vs revise and resubmit: what each stamp lets you do
The difference between approved as noted and revise and resubmit on an MEP submittal, whether you can order, what to do with the notes, and when to push back.
The short answer
Approved as noted, also called make corrections noted or furnish as corrected, means the submittal is accepted on condition that the noted corrections are made, and the work can proceed without resubmitting unless the stamp asks for it. Revise and resubmit means corrections are needed and the submittal must be reviewed again before anything is ordered or installed. With approved as noted, the notes become part of what you must supply, so they must reach the purchase order.
- Approved as noted
- Proceed with the noted corrections; resubmit only if asked
- Revise and resubmit
- Do not order; correct and resubmit for another review
- Defined in
- Section 01 33 00 and the reviewer’s stamp legend
- Risk
- Notes that never reach the purchase order
Side by side
| Approved as noted | Revise and resubmit | |
|---|---|---|
| Other names | Make corrections noted; furnish as corrected; no exceptions taken except as noted | Revise and resubmit; amend and resubmit; returned for corrections |
| Can you order? | Yes, with the corrections applied | No |
| Do you resubmit? | Only if the stamp or notes ask for it | Yes, the whole package or the affected items |
| Review time | None added, unless a resubmittal is requested | Another full review period under 01 33 00 |
| What the notes mean | Instructions that change what you supply | Problems you must solve before approval |
| Typical reasons | Minor option changes, a missing accessory, a finish or voltage correction | Wrong product, missing data, conflicts with the design |
Approved as noted: handle the notes before ordering
The approved-as-noted stamp feels like a pass, which is why its notes are so often lost. A note that changes a voltage, adds a smoke detector or requires a stainless drain pan is a change to the order. If the order goes out as quoted, the equipment arrives as quoted, and the noted correction is still owed.
List every note
Read every page of the returned submittal, not only the stamp. Notes are often written beside a single row of a data table.
Classify each note
Changes to the order, information to coordinate with another trade, or a request for more data. Each needs a different action.
Send order changes to the supplier in writing
Ask for a revised quote or acknowledgment that shows each correction, with any price or lead-time change.
Check the purchase order against the notes
Before release, compare the order line by line with the approved submittal and its notes. See buyout.
Disagree promptly
If a note changes scope or cost, raise it with the architect before ordering. Proceeding without objection is usually taken as acceptance.
- Stamp
- Approved as noted
- Note on page 8
- Provide 460 V unit; 208 V shown does not match E-601
- Order change
- Model number voltage code changes; new electrical data
- Electrical coordination
- MCA and MOP at 460 V go to the electrical contractor
- If the note is missed
- A 208 V unit arrives for a 460 V circuit
See voltage mismatches for why this one note matters so much.
Revise and resubmit: get it right the second time
- Answer every comment in writing on the resubmittal, saying where each correction is.
- Cloud or highlight what changed since the previous submission, so the reviewer can focus on it.
- Use the next revision number from 01 33 00, such as 23 21 23-001.1.
- Do not add unrelated changes; they reset the review.
- Check the resubmittal does not miss the original review’s notes on other items.
Each resubmittal costs a full review period. On long-lead equipment, one revise-and-resubmit can move the delivery date by weeks, which is why the contractor’s own review before the first submission matters. See how to review a cut sheet.
Mixed results on one package
A package covering many tags often comes back with different actions for different items: the pumps approved as noted, one pump rejected, the accessories marked revise and resubmit. Treat each item by its own action. Order what is approved, resubmit what is not, and keep the register showing each item’s status rather than one status for the package.
- Split the resubmittal so the approved items are not reviewed again and the review period is spent only on the open ones.
- Check whether an open item affects an approved one, for example a rejected motor that changes the pump’s electrical data.
- Tell the supplier in writing which items are released and which are on hold, so nothing open is manufactured.
Rejected and other stamps
| Action | Meaning |
|---|---|
| No exceptions taken, or approved | Proceed as submitted |
| Rejected | Does not comply; submit a different product or a complete new submittal |
| Reviewed, or for record only | Informational submittals, recorded without an approval action |
| Not reviewed, or returned without action | Not reviewed, often because it was incomplete or not required |
Where Cailar fits
What Cailar does
- Lets the reviewer record the architect’s decision against the exact version of the package that was reviewed.
- Carries the approved package, including its deviation log, into quote requests, so suppliers price what was approved.
What stays with your reviewer
- Read handwritten notes on returned submittals.
- Decide whether to accept or dispute a reviewer’s note.
Questions and answers
Can I order equipment on an approved-as-noted submittal?
Yes, as long as the noted corrections are applied to the order. A resubmittal is needed only if the stamp or a note asks for one.
Can I order on a revise-and-resubmit?
No. Revise and resubmit means the submittal is not approved. Ordering before approval puts the risk of the change on the contractor.
What does make corrections noted mean?
It is another wording of approved as noted: proceed, incorporating the corrections the reviewer marked.
What if I disagree with a note on an approved-as-noted submittal?
Raise it in writing with the architect before ordering, especially if it changes scope or cost. Proceeding without objection is usually treated as acceptance of the note.
How long does a resubmittal take?
Usually the same review period as the original under Section 01 33 00. Long-lead equipment can lose weeks of schedule to one resubmittal.
Does approved as noted mean the engineer accepted every deviation?
Only the deviations that were identified in writing and that the engineer accepted. A difference that was not disclosed stays the contractor’s responsibility, even under an approved-as-noted stamp.
Should I resubmit after an approved-as-noted stamp anyway?
Only if the stamp or a note asks for it, or if the corrections are large enough that you want the engineer to confirm them. Resubmitting unasked spends another review period without changing your obligation to make the corrections.
Sources
Standards and codes this page relies on. Check the edition your project and jurisdiction have adopted.
- CSI MasterFormat, Section 01 33 00 Submittal Procedures
- AIA Document A201-2017, § 3.12 and § 4.2.7