Section 01 33 00 Submittal Procedures: the rules every MEP submittal follows
What Section 01 33 00 requires of every submittal: review periods, numbering, contractor review, deviations, resubmittals and why packages come back unreviewed.
Illustrative example
The short answer
Section 01 33 00 is the Division 01 section that sets how every submittal on the project is prepared, sent, reviewed and returned. It fixes the review period, the file format and numbering, the contractor’s own review before submitting, how deviations must be called out, and what the architect’s action stamps mean. A trade section says what to submit; 01 33 00 says how.
- MasterFormat division
- 01, General Requirements
- Applies to
- Every action, informational and closeout submittal
- Contract basis
- Usually AIA A201 § 3.12 or the equivalent general conditions
- Read with
- 01 25 00 Substitution Procedures, 01 78 23 O&M Data
What Section 01 33 00 controls
Division 01 holds the procedures that apply to the whole contract. Section 01 33 00 is the one MEP project managers read most, because it decides how much time a submittal will take and what gets it returned without review. The trade sections in Divisions 21 to 26 list what to submit, in Part 1 of each section. They rarely repeat the procedure and instead point back to 01 33 00.
| Article | What it usually says | What it means for you |
|---|---|---|
| Definitions | Action, informational and closeout submittals | Only action submittals come back with a stamp; the rest are recorded |
| Submittal schedule | A list of submittals with dates, due early in the job | Your register has to exist and be sent within a set number of days after award |
| Coordination | Submit related items together; coordinate with other trades | Equipment that depends on another trade’s data can be returned as uncoordinated |
| Review time | A set number of working days, longer for resubmittals or coordination | Plan release dates around it; it is the slack you do not control |
| Format | PDF, bookmarked, one section per package, named a set way | A package in the wrong format can be returned unreviewed |
| Identification | Numbering, cover sheet fields, transmittal form | Use the project’s numbering, not your own |
| Contractor’s review | Contractor reviews and stamps before submitting | The architect is not your first reviewer |
| Deviations | Deviations must be identified in writing | Unmarked deviations are not approved by the architect’s action |
| Architect’s action | Meaning of each stamp | Approved as noted is not a release to order something different |
| Delegated design | Professional engineer’s seal and certification | Seismic, sprinkler and similar submittals need a licensed engineer |
Review periods and what they cost the schedule
Most versions of 01 33 00 allow the architect a fixed number of working days for an initial review, often 10 to 15, and a longer period when the submittal needs coordination with other trades or the engineer’s consultants. Resubmittals usually get the same period again. Two review cycles on a long-lead item can therefore use six weeks or more before the release date.
- Chiller needed on site
- Week 40
- Manufacturer lead time after release
- 18 weeks
- Release and order processing
- 1 week
- Two review cycles at 15 working days
- 6 weeks
- Rep preparation and contractor review
- 2 weeks
- Submit by
- Week 13
If the submittal goes out in week 16 instead, the chiller arrives in week 43. The review period in 01 33 00 is fixed; only the start date is yours.
The contractor’s review comes first
Under AIA A201 § 3.12.5 and most similar general conditions, the contractor reviews each submittal for compliance with the contract documents and approves it before sending it on. By submitting, the contractor states that field measurements, materials and coordination have been checked. Section 01 33 00 usually requires a stamp or signed statement to that effect, and many architects return a package without it.
This is the step where a mechanical or electrical contractor catches what the rep missed: the wrong voltage, a missing accessory, an option that does not match the schedule. See voltage mismatches and the MCA and MOP check for two of the most common.
Deviations must be called out in writing
A201 § 3.12.8 says the contractor is not relieved of responsibility for deviations from the contract documents by the architect’s approval of a submittal, unless the contractor informed the architect of the deviation in writing and the architect gave written approval of that specific deviation. Section 01 33 00 turns that into a procedure, usually a deviation statement on the cover sheet or a separate list.
- List every place the submitted product differs from the specification or the schedule, even if you believe it is equal or better.
- Give the spec paragraph or schedule cell, the specified value, the submitted value and the page in the submittal.
- A different manufacturer than the basis of design is not a deviation if it is a named alternate; it is a substitution if it is not named. Substitutions follow 01 25 00.
- Write “no deviations” only after checking. A cover that says none while the data shows one is the worst case: the deviation is still yours.
Why packages come back without review
| Reason | Avoid it by |
|---|---|
| No contractor review stamp or signature | Stamping after your own review, every package |
| Several spec sections in one package | One section per package unless 01 33 00 allows otherwise |
| Product data for the whole line, nothing marked | Marking the model, size and options supplied for each tag |
| Missing items listed in Part 1 of the section | Checking the package against the section’s submittal list before sending |
| Wrong numbering or file naming | Using the project’s convention from 01 33 00 |
| Unrequested submittals | Sending only what is required; extra items may be returned unreviewed |
| Substitution submitted as a regular submittal | Following 01 25 00 and its deadline |
Architect’s action stamps
The stamp vocabulary is defined in 01 33 00 and varies by firm. The four most common actions are below. Whatever the wording, read the notes before ordering: an approved-as-noted stamp with a note that changes a voltage is an instruction, not a comment.
| Action | Usual meaning | Can you order? |
|---|---|---|
| No exceptions taken, or approved | Reviewed with no comments | Yes |
| Make corrections noted, or approved as noted | Order with the noted changes; resubmit only if asked | Yes, with the notes applied |
| Revise and resubmit | Changes needed and a new review required | No |
| Rejected | Does not comply; submit something else | No |
Where Cailar fits
What Cailar does
- Checks the submitted values against the confirmed spec requirements and the schedule, so deviations are found before the cover sheet is signed.
- Produces a deviation log with each difference, its page and the reviewer’s decision, and places it in the issued package.
What stays with your reviewer
- Track review periods, transmittals or the architect’s stamps. Your project management system or register does that.
- Decide whether a deviation is acceptable. That is the reviewer’s call and, in the end, the engineer’s.
Questions and answers
What is Section 01 33 00?
Section 01 33 00 Submittal Procedures is the Division 01 specification section that sets how submittals are prepared, transmitted, reviewed and returned on a project. It covers review periods, format, numbering, the contractor’s review and the meaning of the architect’s actions.
How long does the architect have to review a submittal?
The period is set in Section 01 33 00 for each project. Ten to fifteen working days for an initial review is common, with longer periods for submittals that need coordination or consultant review. Resubmittals usually get the same time again.
Does the architect’s approval cover a deviation I did not mention?
No. Under AIA A201 § 3.12.8 and most similar contracts, the contractor remains responsible for a deviation unless it was identified in writing and the architect approved that specific deviation in writing.
Why was my submittal returned without review?
The most common reasons are a missing contractor review stamp, several spec sections combined in one package, product data with nothing marked, missing required items, or a substitution sent as a regular submittal. Section 01 33 00 lists the grounds for each project.
What is the difference between 01 33 00 and the submittal article in a trade section?
The trade section, such as 23 21 23, lists what must be submitted for its products. Section 01 33 00 sets how every submittal is handled. Read both: the trade section for content and 01 33 00 for procedure.
Sources
Standards and codes this page relies on. Check the edition your project and jurisdiction have adopted.
- CSI MasterFormat, Division 01
- AIA Document A201-2017, General Conditions of the Contract for Construction, § 3.12