Section 01 33 00 Submittal Procedures: the rules every MEP submittal follows

What Section 01 33 00 requires of every submittal: review periods, numbering, contractor review, deviations, resubmittals and why packages come back unreviewed.

Illustration: a transmittal checked against Section 01 33 00. The contractor stamp, single-section package and bookmarks are in order, but the cover claims no deviations while page 9 shows a different refrigerant.

Illustrative example

The short answer

Section 01 33 00 is the Division 01 section that sets how every submittal on the project is prepared, sent, reviewed and returned. It fixes the review period, the file format and numbering, the contractor’s own review before submitting, how deviations must be called out, and what the architect’s action stamps mean. A trade section says what to submit; 01 33 00 says how.

MasterFormat division
01, General Requirements
Applies to
Every action, informational and closeout submittal
Contract basis
Usually AIA A201 § 3.12 or the equivalent general conditions
Read with
01 25 00 Substitution Procedures, 01 78 23 O&M Data

What Section 01 33 00 controls

Division 01 holds the procedures that apply to the whole contract. Section 01 33 00 is the one MEP project managers read most, because it decides how much time a submittal will take and what gets it returned without review. The trade sections in Divisions 21 to 26 list what to submit, in Part 1 of each section. They rarely repeat the procedure and instead point back to 01 33 00.

Typical articles in 01 33 00 and what they mean for MEP
ArticleWhat it usually saysWhat it means for you
DefinitionsAction, informational and closeout submittalsOnly action submittals come back with a stamp; the rest are recorded
Submittal scheduleA list of submittals with dates, due early in the jobYour register has to exist and be sent within a set number of days after award
CoordinationSubmit related items together; coordinate with other tradesEquipment that depends on another trade’s data can be returned as uncoordinated
Review timeA set number of working days, longer for resubmittals or coordinationPlan release dates around it; it is the slack you do not control
FormatPDF, bookmarked, one section per package, named a set wayA package in the wrong format can be returned unreviewed
IdentificationNumbering, cover sheet fields, transmittal formUse the project’s numbering, not your own
Contractor’s reviewContractor reviews and stamps before submittingThe architect is not your first reviewer
DeviationsDeviations must be identified in writingUnmarked deviations are not approved by the architect’s action
Architect’s actionMeaning of each stampApproved as noted is not a release to order something different
Delegated designProfessional engineer’s seal and certificationSeismic, sprinkler and similar submittals need a licensed engineer

Review periods and what they cost the schedule

Most versions of 01 33 00 allow the architect a fixed number of working days for an initial review, often 10 to 15, and a longer period when the submittal needs coordination with other trades or the engineer’s consultants. Resubmittals usually get the same period again. Two review cycles on a long-lead item can therefore use six weeks or more before the release date.

Worked example: when the chiller submittal must leave your office
Chiller needed on site
Week 40
Manufacturer lead time after release
18 weeks
Release and order processing
1 week
Two review cycles at 15 working days
6 weeks
Rep preparation and contractor review
2 weeks
Submit by
Week 13

If the submittal goes out in week 16 instead, the chiller arrives in week 43. The review period in 01 33 00 is fixed; only the start date is yours.

The contractor’s review comes first

Under AIA A201 § 3.12.5 and most similar general conditions, the contractor reviews each submittal for compliance with the contract documents and approves it before sending it on. By submitting, the contractor states that field measurements, materials and coordination have been checked. Section 01 33 00 usually requires a stamp or signed statement to that effect, and many architects return a package without it.

This is the step where a mechanical or electrical contractor catches what the rep missed: the wrong voltage, a missing accessory, an option that does not match the schedule. See voltage mismatches and the MCA and MOP check for two of the most common.

Deviations must be called out in writing

A201 § 3.12.8 says the contractor is not relieved of responsibility for deviations from the contract documents by the architect’s approval of a submittal, unless the contractor informed the architect of the deviation in writing and the architect gave written approval of that specific deviation. Section 01 33 00 turns that into a procedure, usually a deviation statement on the cover sheet or a separate list.

  • List every place the submitted product differs from the specification or the schedule, even if you believe it is equal or better.
  • Give the spec paragraph or schedule cell, the specified value, the submitted value and the page in the submittal.
  • A different manufacturer than the basis of design is not a deviation if it is a named alternate; it is a substitution if it is not named. Substitutions follow 01 25 00.
  • Write “no deviations” only after checking. A cover that says none while the data shows one is the worst case: the deviation is still yours.

Why packages come back without review

Returned without action, and how to avoid it
ReasonAvoid it by
No contractor review stamp or signatureStamping after your own review, every package
Several spec sections in one packageOne section per package unless 01 33 00 allows otherwise
Product data for the whole line, nothing markedMarking the model, size and options supplied for each tag
Missing items listed in Part 1 of the sectionChecking the package against the section’s submittal list before sending
Wrong numbering or file namingUsing the project’s convention from 01 33 00
Unrequested submittalsSending only what is required; extra items may be returned unreviewed
Substitution submitted as a regular submittalFollowing 01 25 00 and its deadline

Architect’s action stamps

The stamp vocabulary is defined in 01 33 00 and varies by firm. The four most common actions are below. Whatever the wording, read the notes before ordering: an approved-as-noted stamp with a note that changes a voltage is an instruction, not a comment.

Common action stamps
ActionUsual meaningCan you order?
No exceptions taken, or approvedReviewed with no commentsYes
Make corrections noted, or approved as notedOrder with the noted changes; resubmit only if askedYes, with the notes applied
Revise and resubmitChanges needed and a new review requiredNo
RejectedDoes not comply; submit something elseNo

Where Cailar fits

What Cailar does

  • Checks the submitted values against the confirmed spec requirements and the schedule, so deviations are found before the cover sheet is signed.
  • Produces a deviation log with each difference, its page and the reviewer’s decision, and places it in the issued package.

What stays with your reviewer

  • Track review periods, transmittals or the architect’s stamps. Your project management system or register does that.
  • Decide whether a deviation is acceptable. That is the reviewer’s call and, in the end, the engineer’s.

Questions and answers

What is Section 01 33 00?

Section 01 33 00 Submittal Procedures is the Division 01 specification section that sets how submittals are prepared, transmitted, reviewed and returned on a project. It covers review periods, format, numbering, the contractor’s review and the meaning of the architect’s actions.

How long does the architect have to review a submittal?

The period is set in Section 01 33 00 for each project. Ten to fifteen working days for an initial review is common, with longer periods for submittals that need coordination or consultant review. Resubmittals usually get the same time again.

Does the architect’s approval cover a deviation I did not mention?

No. Under AIA A201 § 3.12.8 and most similar contracts, the contractor remains responsible for a deviation unless it was identified in writing and the architect approved that specific deviation in writing.

Why was my submittal returned without review?

The most common reasons are a missing contractor review stamp, several spec sections combined in one package, product data with nothing marked, missing required items, or a substitution sent as a regular submittal. Section 01 33 00 lists the grounds for each project.

What is the difference between 01 33 00 and the submittal article in a trade section?

The trade section, such as 23 21 23, lists what must be submitted for its products. Section 01 33 00 sets how every submittal is handled. Read both: the trade section for content and 01 33 00 for procedure.

Sources

Standards and codes this page relies on. Check the edition your project and jurisdiction have adopted.

Bring us one submittal.

Send us one submittal and its spec section. We run the review with you, and you keep the report.

Run a pilot