How to build an MEP submittal register from the spec book
A step-by-step method for turning Division 21 to 26 spec sections into a submittal register, with columns, a numbering scheme and back-scheduled dates.
The short answer
Read Section 01 33 00 for the project’s submittal rules, then go through Part 1 of every spec section in your scope and make one register row for each action, informational and closeout submittal it asks for. Give each row a number, the paragraph it came from, the tags it covers, who prepares it, and a submit-by date worked back from when the equipment must be on site.
- Start with
- Section 01 33 00 Submittal Procedures and the latest addenda
- Where items are listed
- Part 1, the Submittals article of each section
- One row per
- Submittal item, not per spec section
- Dates
- Worked back from need-on-site, through lead time and review time
What a submittal register is for
The register is the contractor’s list of everything the specifications require to be submitted, with who owes it and when. It is what the project manager uses to chase suppliers, what the architect’s office uses to log reviews, and what proves at closeout that every required item was delivered. A good register is built from the specifications themselves, not from a previous job’s list, because two projects with the same section number can ask for different things.
Step by step
Gather the current documents
Use the conformed spec book or the bid set with every addendum and bulletin issued so far. Pull the equipment schedules from the drawings as well; the register links submittals to tags, and the tags live on the schedules.
Read Section 01 33 00 first
Division 01 sets the rules for every other section: the review period (often 10 to 15 working days, longer for resubmittals or delegated design), the required format, the numbering convention, whether electronic submittals are accepted, and how many times the architect will review before charging for it. Note Section 01 25 00 for how substitutions must be requested, because those follow a different path.
List every section in your scope
For a mechanical contractor that is usually Division 23 plus the Division 22 and 21 sections in the contract, and the common work sections such as 23 05 13, 23 05 29, 23 05 48 and 23 05 93. Use the table of contents and the scope letter together, since common work sections are easy to miss.
Read Part 1 of each section, line by line
Under CSI SectionFormat, Part 1 holds the Submittals articles, usually split into action submittals (product data, shop drawings, samples), informational submittals (certificates, test reports, qualification data) and closeout submittals (O&M data, warranties, extra materials). Make one row for each item, and copy the paragraph number so anyone can find the requirement again.
Search Parts 2 and 3 for hidden submittals
Requirements such as “submit seismic restraint calculations”, “submit field alignment report” or “submit startup report” are often written into Part 3 rather than Part 1. Search each section for the words submit, furnish and provide, and add what you find.
Link rows to equipment tags
One section often covers many tags. Section 23 21 23 may cover P-1 to P-8, and some pumps may come from a different manufacturer than others. Record the tags on each row so a missing tag is visible.
Number the rows
Use the section number plus a sequence, and a revision suffix for resubmittals, unless 01 33 00 prescribes a format. 23 21 23-001.0 is the first pump product data; 23 21 23-001.1 is its first resubmittal.
Work the dates backwards
Start from the date the equipment must be on site, then subtract delivery lead time, release time, the review period, a resubmittal allowance and your own preparation time. The result is the date the submittal must leave your office. Long-lead equipment such as switchgear, chillers, generators and air handlers usually sets the earliest dates on the job.
Mark delegated design and closeout items
Delegated-design submittals, such as seismic restraint design or fire sprinkler hydraulic calculations, need a licensed engineer’s seal and more time. Closeout items are not due until the end, but listing them now prevents the scramble for O&M manuals and warranties at turnover.
Keep it current
Every addendum, bulletin and change directive can add, remove or change a submittal. Re-read the affected sections when they are issued and record the document that changed each row.
Columns to include
| Column | Example | Why |
|---|---|---|
| Number | 23 21 23-001.0 | Unique reference used in every transmittal |
| Spec section and paragraph | 23 21 23, 1.4.A | Lets anyone find the requirement |
| Description | Hydronic pumps, product data | What is being submitted |
| Type | Action, product data | Separates action, informational and closeout items |
| Tags covered | P-1 to P-4 | Shows when a tag has no submittal |
| Responsible party | Pump supplier, via mechanical contractor | Who must produce it |
| Need on site | 2027-03-15 | The date everything works back from |
| Lead time | 10 weeks | From release to delivery |
| Submit by | 2026-12-14 | The date it must leave your office |
| Status and action | Approved as noted | The reviewer’s action, with the date returned |
| Changed by | Addendum 2 | Traces rows added or edited after bid |
Keep the status vocabulary the same as the architect’s stamp: approved, approved as noted, revise and resubmit, rejected. A row marked approved as noted is not finished until the notes have been checked against what is being ordered.
What gets missed most often
- Common work sections such as motors, hangers, vibration isolation, identification and testing and balancing.
- Submittals written into Part 3, such as startup and alignment reports.
- Qualification data for installers, welders and testing agencies.
- Items that appear only on the drawings, such as a schedule note asking for a sound report.
- Extra stock and spare parts listed in closeout sections, which are easy to leave off the purchase order.
- Electrical data that must match another trade, such as motor voltages checked against the panel schedules. See voltage mismatches.
After the register: reviewing each item
The register tells you what to submit and when. It does not tell you whether a submittal answers its spec section. That is a separate check for each row: read the requirements in the section and the schedule, find each one in the manufacturer’s data, and note every value that is missing or different. The hydronic pump guide shows what that check looks like for one section.
Where Cailar fits
What Cailar does
- Reads each spec section you upload and lists the requirements it found, with page references, for a reviewer to confirm.
- Checks each submittal against the confirmed requirements and the schedule, citing the page behind each value.
What stays with your reviewer
- Build or maintain the submittal register itself. Most teams keep that in Procore, another project management system or a spreadsheet.
- Set dates, chase suppliers or send transmittals to the architect.
Questions and answers
What is a submittal register?
A submittal register, also called a submittal log or schedule, is the list of every submittal the specifications require, with its spec reference, the party responsible, its due date and its review status. It is used to track submittals from preparation through approval and closeout.
Where do I find the submittal requirements in a spec section?
In Part 1 of the section, in the articles titled Action Submittals, Informational Submittals and Closeout Submittals, or a single Submittals article on older specs. Also search Parts 2 and 3, where some items such as startup reports are written.
What is the difference between action and informational submittals?
Action submittals, such as product data and shop drawings, need the architect or engineer to review and return them with an action. Informational submittals, such as certificates and test reports, are for the record and are not stamped with an action.
How long does submittal review take?
Section 01 33 00 sets the period for each project. Ten to fifteen working days is common for an initial review, with longer periods for delegated design or submittals that need coordination with other trades. Plan for at least one resubmittal on major equipment.
Should the register be one row per spec section?
No. Make one row per submittal item. A single section can require product data, shop drawings, a certificate and closeout documents, each due at a different time and each reviewed separately.
Sources
Standards and codes this page relies on. Check the edition your project and jurisdiction have adopted.
- CSI MasterFormat and SectionFormat
- AIA Document A201, General Conditions of the Contract for Construction, § 3.12