Section 23 21 23 Hydronic Pumps: what the submittal must prove
What Section 23 21 23 asks for, the 14 values to check on a hydronic pump submittal, how to read the curve, and the reasons pump submittals come back rejected.
Illustrative example
The short answer
Section 23 21 23 covers the circulating pumps for chilled water, heating hot water and condenser water systems. A complete pump submittal shows the scheduled flow and head marked on a curve for the impeller actually supplied, a motor that does not overload anywhere on that curve, and motor, seal, pressure and connection data that match the schedule and the electrical drawings.
- MasterFormat division
- 23, Heating, Ventilating and Air Conditioning
- Typical equipment
- In-line, end-suction, split-case pumps and circulators
- Schedule to compare
- Pump schedule on the mechanical drawings, motor circuits on the panel schedules
- Sections it leans on
- 23 05 13, 23 05 48, 23 21 13, 23 21 16, 26 29 23
What Section 23 21 23 covers
In MasterFormat, 23 21 23 is the section for pumps that move water or glycol through closed and open HVAC loops. Most projects use it for chilled water primary and secondary pumps, heating hot water pumps, condenser water pumps and small wet-rotor circulators. Domestic water booster pumps belong in 22 11 23, and fire pumps in Division 21, so a pump that serves the plumbing or sprinkler system should not be submitted under this section.
The section usually names a basis-of-design manufacturer and lists acceptable alternates. It fixes the pump construction (casing, impeller, shaft and seal), the motor requirements by reference to Section 23 05 13, and the selection rules the engineer cares about, such as where on the curve the duty point may sit. The schedule on the drawings then gives each tag its flow, head, fluid, motor size and electrical data.
| Type | Where it is used | What to watch on the submittal |
|---|---|---|
| Vertical in-line | Secondary loops, smaller plants, mechanical rooms short on floor space | Pipe support at the pump, motor weight on the piping, seal access |
| End-suction, close-coupled | Small to mid-size loops | Motor frame and impeller on one shaft, so a motor swap changes the pump |
| End-suction, base-mounted | Primary chilled water, condenser water | Base and grout, coupling guard, field alignment, inertia base if scheduled |
| Horizontal split-case | Large plants and high flows | Suction and discharge orientation, rotation, weight on the pad |
| Wet-rotor circulator | Small zones, domestic recirculation on some jobs | Fixed speed or ECM, voltage, whether it is listed for the fluid temperature |
What the submittal package should contain
Part 1 of the section lists the action submittals. Most versions ask for the same four things, and a package that leaves one out is incomplete before anyone looks at a number.
- Product data for each tag: model, construction materials, seal type, working pressure and temperature ratings, and connection sizes.
- A performance curve for each tag with the duty point marked, the impeller diameter stated, and the efficiency, BHP and NPSH required at that point.
- Motor data: horsepower, speed, voltage, phase, frequency, enclosure, efficiency and whether the motor is inverter rated.
- Shop drawings or dimensional data with weights, so the structural and housekeeping pad work can be checked.
Informational and closeout submittals usually follow: field alignment reports for base-mounted pumps, startup reports, and operation and maintenance data. Track those on the submittal register as separate rows, because they are due at different times.
The values to check on every pump
These are the values that decide whether a pump submittal can be approved. The left column is where the requirement usually lives; the right column is where the submittal answers it.
| Value | Requirement comes from | Where the submittal shows it | Common problem |
|---|---|---|---|
| Flow (GPM) | Pump schedule | Curve duty point | Curve shows the catalog point, not the scheduled one |
| Head (ft) | Pump schedule | Curve duty point | Head rounded or taken from a different impeller line |
| Fluid and glycol percentage | Schedule or 23 25 00 | Selection printout | Selected on water while the system runs 30 percent propylene glycol |
| Efficiency at duty point | Spec selection rules | Curve | Duty point far to the right of best efficiency |
| Impeller diameter | Spec selection rules | Curve header | Maximum impeller supplied, leaving no room to trim or upsize |
| Motor horsepower | Pump schedule | Motor data | Motor sized at the duty point but overloads at the end of the curve |
| Speed (RPM) | Pump schedule | Curve header | 1,750 RPM scheduled, 3,500 RPM submitted to reach a smaller frame |
| Voltage, phase, frequency | Pump schedule and panel schedule | Motor data | See voltage mismatches |
| Motor enclosure and efficiency | 23 05 13 | Motor data | ODP submitted where TEFC is required |
| Inverter rating and shaft grounding | 23 05 13 and 26 29 23 | Motor data | Pump on a VFD with no inverter-duty statement or bearing protection |
| Working pressure | 23 21 23 and the piping test pressure | Product data | 175 psig casing on a system tested at 225 psig |
| Seal and elastomers | 23 21 23 | Product data | Elastomer not stated or not suitable for glycol or the loop temperature |
| Connections | Drawings | Dimensional data | Flange size or rating differs from the piping |
| Weight | Structural and pad details | Dimensional data | Operating weight missing, so the inertia base cannot be checked |
Reading the pump curve
The curve is the one page that decides most pump reviews. Check four things on it, in this order.
Find the duty point
The scheduled flow and head should be marked on the curve for the impeller diameter supplied. If the rep marked a different point, or no point, return it. A curve with no mark proves nothing about this tag.
Check where it sits against best efficiency
Many specs require the duty point within a set band of the best efficiency point, or inside the manufacturer’s preferred operating region as defined in ANSI/HI 9.6.3. A point well to the right of best efficiency runs inefficiently and closer to cavitation; a point well to the left recirculates and wears the seal.
Follow the curve to runout
Read the BHP at the far right end of the impeller line. If the spec calls for a non-overloading motor, that BHP must not exceed the motor nameplate horsepower. This matters most for parallel pumps: when one pump runs alone it moves far down the system curve and can overload a motor that was fine at the design point.
Check NPSH on open loops
Condenser water pumps drawing from a cooling tower basin have the least margin. Compare the NPSH required at the duty point with the NPSH available the engineer calculated. Closed loops with proper fill pressure rarely have this problem.
- Scheduled duty
- 220 GPM at 68 ft
- BHP at duty point
- 5.6 BHP
- BHP at end of curve
- 7.1 BHP
- Motor supplied
- 7.5 HP
- Result
- Non-overloading across the curve
If the rep had offered a 5 HP motor because 5.6 BHP is within the service factor, the motor would overload at runout. Service factor is not a sizing margin.
Glycol changes the selection
Propylene and ethylene glycol are denser and more viscous than water, especially when cold. A pump selected on water at the scheduled flow and head will deliver less head and draw more power on a 30 or 40 percent glycol loop. Ask for a selection printout that states the fluid, concentration and temperature. If the schedule names a glycol loop and the curve says water, the submittal has not been selected for this project.
Glycol also affects the seal. Check that the elastomer and seal faces are rated for the fluid and the loop temperature. Heating hot water loops above about 200 °F and chilled water loops with glycol are both common reasons manufacturers offer more than one seal option.
Coordination with the electrical drawings
The pump is a Division 23 item but its motor is fed from Division 26, and most pump rejections that reach the field are electrical. Compare the motor data on the submittal with the panel schedule and the motor circuit on the electrical drawings, not only with the mechanical schedule.
- Voltage and phase match the circuit. A 208–230 V motor and a 460 V motor of the same horsepower are different motors with different full-load current.
- If a VFD is shown, confirm who supplies it. Some specs require a VFD under Section 26 29 23, others accept a pump with an integrated drive. The submittal must say which.
- Integrated-drive pumps change the electrical scope: there may be no separate drive to mount, but the circuit, disconnect and harmonic requirements still need to match.
- Horsepower changes after selection move the breaker and conductor size. If the rep upsized from 5 to 7.5 HP, tell the electrical contractor before their panels are released.
Why pump submittals come back rejected
| Reason | How to avoid it |
|---|---|
| No duty point on the curve, or the wrong one | Ask the rep to mark the scheduled point for each tag before you submit |
| Motor overloads at runout | Check BHP at the end of the impeller line against motor horsepower |
| Selected on water for a glycol loop | Require a selection printout that states the fluid |
| Wrong voltage or phase | Check against the panel schedule, not only the mechanical schedule |
| Approved equal without the comparison the spec asks for | Include a side-by-side with the basis of design |
| Inverter rating or bearing protection missing | Confirm 23 05 13 requirements when the pump runs on a VFD |
| Working pressure below the test pressure | Compare the casing rating with the hydrostatic test in 23 21 13 |
Where Cailar fits
What Cailar does
- Lists the requirements found in Section 23 21 23 and the pump schedule, each with the page it came from, for a reviewer to confirm.
- Finds the matching value on the submittal page and compares units and electrical values in code, so a 208–230 V motor against a 460 V schedule is flagged with both pages cited.
- Marks a requirement as not stated when the submittal has no value for it, such as a missing seal elastomer, and holds the package until a reviewer resolves it.
What stays with your reviewer
- Judge where the duty point sits on the curve or whether a pump is a good selection. That stays with the reviewer and the engineer.
- Calculate NPSH available, glycol corrections or system curves.
Questions and answers
What is Section 23 21 23 in a specification?
Section 23 21 23 Hydronic Pumps is the MasterFormat section for pumps in HVAC water and glycol systems, such as chilled water, heating hot water and condenser water pumps. It sets the pump construction, motor requirements and selection rules, and lists what the pump submittal must contain.
What should a hydronic pump submittal include?
Product data with construction and pressure ratings, a performance curve for each tag with the scheduled duty point marked, motor data including voltage and enclosure, and dimensional data with weights. Many specs also require a selection printout that states the fluid and glycol concentration.
What does non-overloading mean on a pump submittal?
It means the motor horsepower is at least the brake horsepower the pump draws anywhere on its curve for the supplied impeller, including at runout on the far right. Check the BHP at the end of the curve, not only at the duty point.
Are domestic water pumps covered by 23 21 23?
No. Domestic water booster and circulating pumps belong in Division 22, usually Section 22 11 23. Fire pumps are in Division 21. Submitting them under 23 21 23 is a common reason a package is returned for being filed under the wrong section.
Does the pump need its own VFD submittal?
It depends on the spec. If the drive is specified in Section 26 29 23 it is usually submitted by the electrical contractor. If the pump has an integrated drive, the drive data belongs in the pump submittal. Check which section the drawings and specs assign it to before you submit.
Sources
Standards and codes this page relies on. Check the edition your project and jurisdiction have adopted.
- CSI MasterFormat, Division 23
- ANSI/HI 9.6.3, Rotodynamic Pumps: Guideline for Operating Regions
- NEMA MG 1, Motors and Generators
- 10 CFR 431 Subpart Y, federal energy conservation standards for pumps