Section 01 25 00 Substitution Procedures: when and how to propose another product
When an MEP product counts as a substitution, the deadlines in Section 01 25 00, what the request must prove, and the costs it moves to the contractor.
Illustrative example
The short answer
Section 01 25 00 sets the rules for proposing a product that the specifications do not name. It fixes the deadline, the request form, the comparison the contractor must provide and the representations the contractor makes by submitting. A product that is not the basis of design or a named alternate is a substitution, and it is not approved through an ordinary submittal.
- MasterFormat division
- 01, General Requirements
- Two kinds
- Before bid (prior approval) and after award (for cause or convenience)
- Common form
- CSI Form 13.1A Substitution Request, or the architect’s own
- Read with
- 01 33 00 Submittal Procedures, 01 60 00 Product Requirements
Substitution, named alternate or approved equal
Specifications name products in a few ways, and the label decides which path a product takes. Section 01 60 00 Product Requirements usually defines the terms; 01 25 00 then applies to anything outside them.
| How the spec names it | Example wording | Path |
|---|---|---|
| Basis of design | Basis of design: Manufacturer A, model X | Ordinary submittal |
| Named alternate | Subject to compliance, provide one of: A, B, C | Ordinary submittal, but it must meet every requirement |
| Or approved equal | Manufacturer A or approved equal | Depends on 01 60 00; often a submittal with a comparison, sometimes a substitution request |
| Sole source | No substitutions | No alternate accepted |
| Anything not named | Manufacturer D, not listed | Substitution under 01 25 00 |
Named alternates still have to meet the schedule and every requirement written around the basis of design. A different manufacturer’s air handler at the same airflow may still be heavier, draw more current or need a different curb. Those differences are deviations and have to be listed under 01 33 00.
Deadlines: before bid and after award
Before bid: prior approval
Many projects accept substitution requests during bidding up to a fixed number of days before bids are due. Approved products are added by addendum, so every bidder can price them. After that date, bidders must price the named products.
After award: for cause
A substitution for cause is one the contractor needs because the specified product is unavailable, discontinued, cannot meet a code or warranty requirement, or cannot be delivered in time through no fault of the contractor. It is usually accepted any time the cause arises, with evidence.
After award: for convenience
A substitution the contractor prefers, for price or lead time, is often accepted only within a set window after the notice to proceed, such as 60 days, and only if it offers the owner a benefit. Some specifications do not allow it at all.
Missing the window is the most common reason a good alternate is refused. Put the 01 25 00 deadlines at the top of the submittal register, before any product submittal dates.
What the request must contain
- The specified product and the proposed product, with the spec section and paragraph.
- A point-by-point comparison of every significant property: capacity, efficiency, dimensions, weight, electrical data, materials, sound, controls and warranty.
- Product data for the proposed product, marked for the model and options proposed.
- The effect on other work: structure, electrical feeders and breakers, piping and duct connections, controls, access and the schedule.
- The change in contract sum, and any change in contract time.
- Projects where the product has been used, if the architect asks for them, and the manufacturer’s local service availability.
- Basis of design MCA, 460/3/60
- 38 A
- Proposed unit MCA
- 46 A
- Conductors on the drawings
- 8 AWG Cu, 50 A at 75 °C
- Basis MOP and breaker
- 50 A, 50 A breaker
- Proposed MOP
- 60 A; 50 A breaker still at or below MOP
- Result
- No electrical change, but say so in the request
Had the proposed MCA been 52 A, the conductors would grow to 6 AWG and the electrical contractor’s change would belong in the substitution request. See MCA and MOP.
What the contractor represents by submitting
Most versions of 01 25 00 say that by requesting a substitution, the contractor represents that it has investigated the proposed product and found it equal or better, that it will provide the same warranty, that it will coordinate and pay for any changes to other work, and that it waives claims for added cost or time caused by the substitution. Read that paragraph before submitting: it usually moves the cost of redesign, structural review and other trades’ changes onto the contractor.
Why substitution requests are refused
| Reason | Fix |
|---|---|
| Submitted after the deadline | Track 01 25 00 dates from the day of award |
| Sent as an ordinary submittal | Use the substitution form and procedure |
| Comparison covers only the headline ratings | Compare every property in the spec section and schedule |
| Effect on other trades not stated | List structural, electrical, piping and controls effects, even when the answer is none |
| No benefit to the owner for a convenience request | State the saving or schedule gain offered |
| Missing data such as sound or leakage | Get the data from the manufacturer before submitting |
Where Cailar fits
What Cailar does
- Checks the proposed product against the same confirmed requirements as the basis of design, so the comparison covers every property in the section and schedule.
- Marks values the proposed product’s data does not state, such as casing leakage, so they are requested before the substitution goes out.
What stays with your reviewer
- Prepare or send the substitution request form, or track 01 25 00 deadlines.
- Judge whether a proposed product is equal. The engineer decides that.
Questions and answers
What is Section 01 25 00?
Section 01 25 00 Substitution Procedures is the Division 01 section that sets how a contractor proposes a product not named in the specifications, including deadlines, the request form, the required comparison and the contractor’s representations.
Is an approved equal the same as a substitution?
Not always. If the specification names the product or allows an approved equal under 01 60 00, it may go through an ordinary submittal with a comparison. A product the specification does not name at all is a substitution and follows 01 25 00.
When can I submit a substitution request?
Before bid, up to the prior-approval deadline in the bidding documents. After award, substitutions for cause are usually accepted when the cause arises; substitutions for convenience are often limited to a window after the notice to proceed, or not allowed.
Who pays for changes caused by a substitution?
Under most versions of 01 25 00, the contractor does. By requesting the substitution, the contractor agrees to coordinate and pay for changes to other work and waives claims for added cost or time caused by it.
What is CSI Form 13.1A?
It is the Construction Specifications Institute’s standard substitution request form. It asks for the specified and proposed products, a comparison, the effect on other work, cost and time changes, and the contractor’s representations. Many architects use it or their own version.
Sources
Standards and codes this page relies on. Check the edition your project and jurisdiction have adopted.
- CSI MasterFormat, Division 01
- CSI Form 13.1A, Substitution Request
- AIA Document A201-2017, General Conditions of the Contract for Construction