How to review a cut sheet against its spec section, value by value
A repeatable method for checking a cut sheet against the spec section and schedule: build the requirement list, find each value, read footnotes, convert units.
The short answer
List every requirement for the tag from the spec section, the schedule and its notes, each with its source. Mark the model and options actually supplied on the cut sheet. Then find each requirement on the cut sheet, convert units where needed, check the conditions and footnotes behind the value, and record one of three outcomes: meets, conflicts, or not stated. Every conflict and every missing value becomes a review comment.
- Inputs
- Spec section, schedule row and notes, details, the cut sheet
- Outcomes per requirement
- Meets, conflicts, not stated
- Most missed
- Footnotes, rating conditions and unmarked options
- Output
- A requirement list with page references and comments
Step by step
Confirm the product and section
Check the cover sheet names the right spec section and tags. A pump submitted under the wrong section is reviewed against the wrong requirements.
Build the requirement list
Read Part 2 of the section paragraph by paragraph, the schedule row and its notes, the drawing details that show the equipment, and any other section that mentions it. Write each requirement once, with its source, for example “Casing leakage at 8 in. wg, 23 73 13, 2.3.F”.
Mark what is being supplied
Cut sheets show a product family. Circle or highlight the size, model number and options supplied for each tag. If the rep did not mark them, ask before reviewing; otherwise every value is ambiguous.
Find each requirement
For each line of the list, find the value on the cut sheet for the supplied model and record the page. Use data tables and selection printouts, not marketing summaries.
Check conditions and footnotes
A capacity is only meaningful at its rating conditions. Read the footnotes beside every table: “at 0 in. wg external static”, “at 95 °F ambient”, “typical values”, “with optional coil”.
Convert units
Convert to the units of the requirement before comparing: L/s to CFM, kW to tons or MBH, Pa to in. wg, kPa to ft of head.
Record the outcome
Meets, conflicts, or not stated. Not stated is not a pass; it is a question for the rep.
Write the comments
Write one comment for each conflict or missing value. Name where it is and what the two values are, and quote the spec paragraph or schedule cell it comes from, so the rep can fix it without asking.
A requirement list in practice
| Requirement | Source | Cut sheet value | Page | Outcome |
|---|---|---|---|---|
| 2,400 CFM at 0.75 in. wg | Schedule M-603 | 2,400 CFM at 0.75 in. wg | 3 | Meets |
| Direct drive, EC motor | 23 34 23, 2.2.B | Belt drive | 2 | Conflicts |
| 115/1/60 | Schedule | 115/1/60 | 4 | Meets |
| Sones at design, 10 maximum | Schedule note 4 | Not shown | Not stated | |
| AMCA certified ratings seal | 23 34 23, 1.4.A | Seal shown for air and sound | 1 | Meets |
| Backdraft damper | Schedule note 2 | Option listed, not marked | 6 | Not stated |
Units and conditions
- Airflow 2,500 L/s × 2.119
- 5,297 CFM
- Pressure 250 Pa ÷ 249.1
- 1.00 in. wg
- Cooling 350 kW ÷ 3.517
- 99.5 tons
- Water pressure drop 60 kPa × 0.335
- 20.1 ft of head
- Requirement: 100 tons
- 99.5 tons is 0.5 percent short
Whether 0.5 percent short is acceptable depends on the spec’s tolerance and the engineer. Record it as a conflict and let the reviewer decide; rounding it away hides it.
| Footnote says | What it means |
|---|---|
| Ratings at 0 in. wg external static | Airflow will be lower in a real duct system |
| Typical values | Not guaranteed; ask for certified or tested data |
| With optional coil or option code | The value only applies if that option is ordered |
| Sound power, not pressure | Not directly comparable with an NC or dBA requirement |
| At standard air, sea level | Correct for altitude at high sites |
| Subject to change without notice | Check the cut sheet revision date is current |
Where reviews go wrong
- Reviewing the product family instead of the supplied model and options.
- Treating not stated as meets because the product is probably fine.
- Comparing values at different conditions, such as capacity at a milder ambient. See airflow below schedule.
- Checking the mechanical values and skipping the electrical data. See voltage mismatches.
- Missing requirements that live in schedule notes or other sections, such as accessories. See missing accessories.
Where Cailar fits
What Cailar does
- Suggests a requirement list from the spec sections and schedules you upload, each with its page, for a reviewer to confirm.
- Finds the matching value on the cut sheet, converts common units such as CFM, L/s, in. wg, Pa, MBH and tons in code, and records meets, conflict or missing evidence with both pages cited.
What stays with your reviewer
- Read every footnote’s effect on a value. The reviewer confirms rating conditions.
- Decide whether a small shortfall is acceptable.
Questions and answers
What is a cut sheet?
A manufacturer’s product data sheet showing a product’s performance, dimensions, options and ratings. In a submittal, cut sheets are the product data the contractor submits for review.
How do I know which model on a cut sheet is being supplied?
The submittal should mark it: the size, model number and options for each tag, circled or highlighted. If nothing is marked, ask the rep before reviewing, because the values for different sizes differ.
Is a value that is not on the cut sheet a pass?
No. A requirement the cut sheet does not answer is not stated. Ask for the data. Accepting it unstated means the requirement was never checked.
How do I convert L/s to CFM?
Multiply liters per second by about 2.119. 2,500 L/s is about 5,297 CFM. To convert Pa to inches of water, divide by about 249.1.
What should a review comment include?
Enough for the rep to act without calling you: which tag and page, what was submitted, what is required, and the spec paragraph or schedule cell the requirement comes from.