Product data vs shop drawings: two kinds of MEP submittal, reviewed differently
The difference between product data and shop drawings under AIA A201, MEP examples of each, how each is reviewed, and where coordination drawings fit.
The short answer
Product data is the manufacturer’s standard information about a product: cut sheets, performance curves, ratings and instructions. Shop drawings are drawings, diagrams and schedules prepared specifically for the project by the contractor, a subcontractor or a supplier, such as ductwork layouts, sprinkler layouts or switchboard elevations. Product data proves the product meets the requirements; shop drawings show how this project’s work will be built. Both are action submittals, and neither is a contract document.
- Definitions
- AIA A201-2017 § 3.12.1 shop drawings, § 3.12.2 product data
- Status
- Neither is a contract document (§ 3.12.4)
- Product data proves
- Performance, ratings, construction, options
- Shop drawings prove
- Layout, dimensions, fabrication and installation for this project
Side by side
| Product data | Shop drawings | |
|---|---|---|
| Prepared by | The manufacturer, as standard literature | The contractor, subcontractor or supplier, for this project |
| Typical MEP examples | Cut sheets, pump and fan curves, selection printouts, electrical data | Duct and piping layouts, sprinkler layouts, custom air handler drawings, switchboard and panel drawings |
| What the reviewer checks | Compliance with Part 2 and the schedules | Fit, layout, dimensions, clearances and coordination with other work |
| Must be marked for | The model, size and options supplied | The project’s tags, levels and grid lines |
| Typical timing | Early, especially for long-lead equipment | After product data, once equipment sizes are known |
| Common problem | Unmarked family data covering many models | Drawn from catalog dimensions before the product was approved |
What each must contain
- Product data: the cut sheet for the supplied model with options marked, performance at the scheduled conditions, electrical data for the supplied voltage, dimensions and weights, and the certifications the section requires.
- Shop drawings: plans, sections and details at a stated scale, with tags, sizes, elevations, connection points, supports, access and clearances, and references to the approved product data they rely on.
- Both: the cover sheet, the contractor’s review stamp and the deviation list that Section 01 33 00 requires.
Some submittals are both
Large configured equipment blurs the line. A custom air handler submittal includes manufacturer product data for its fans and coils and project-specific drawings of its sections, splits and connections, prepared for this job. Switchboards and motor control centers are the same: standard component data plus project-specific elevations, one-lines and bus ratings. Review each part for what it is: compliance for the product data, fit and coordination for the drawings.
- Fan curve and selection printout
- Product data: check airflow at total static pressure
- Coil printouts
- Product data: check capacity, rows, face velocity
- Unit drawing with section lengths
- Shop drawing: check fit in the mechanical room
- Connection locations and hands
- Shop drawing: check against piping and duct layouts
- Shipping splits
- Shop drawing: check against the rigging path
See the 23 73 13 air handler page for the product data checks.
Where coordination drawings fit
Coordination drawings, often produced from a shared model, show the MEP trades’ work together to resolve clashes before installation. Many specifications treat them as a separate submittal, sometimes informational rather than action, and many architects review them only for general conformance. They depend on approved product data and shop drawings, so delays upstream push coordination late.
| Submittal | Depends on |
|---|---|
| Product data | Specifications and schedules |
| Shop drawings | Approved product data for sizes and connections |
| Coordination drawings | Shop drawings of every trade in the area |
Samples and informational submittals
A201 § 3.12.3 defines samples as physical examples that illustrate materials, equipment or workmanship and establish standards by which the work will be judged. MEP samples are less common than architectural ones, but they appear for visible items: grille and diffuser finishes, plumbing fixture trim, lighting fixtures in a mockup room, and exposed duct or pipe finishes.
| Type | MEP examples | Reviewed for |
|---|---|---|
| Samples | Diffuser finish, fixture trim, exposed hanger finish | Appearance and the standard the work will be judged against |
| Informational submittals | Certificates, test reports, qualification data, manufacturer instructions | Recorded; usually no approval action |
| Closeout submittals | O&M manuals, warranties, record drawings, extra stock | Completeness at turnover |
Neither is a contract document
A201 § 3.12.4 states that shop drawings, product data and samples are not contract documents. Their purpose is to show how the contractor proposes to meet the contract documents. That is why an approved submittal does not change the contract unless a deviation was identified in writing and approved; see how to write a deviation list.
Where Cailar fits
What Cailar does
- Checks product data against the confirmed spec and schedule requirements, value by value, with pages cited.
- Keeps the manufacturer’s original pages in the issued package, with review stamps that open in Bluebeam Revu.
What stays with your reviewer
- Review shop drawing layouts, clearances or coordination drawings.
- Detect clashes between trades.
Questions and answers
What is the difference between product data and shop drawings?
Product data is the manufacturer’s standard literature about a product, such as cut sheets and performance curves. Shop drawings are drawings and schedules prepared specifically for the project, such as duct layouts or switchboard elevations.
Are shop drawings contract documents?
No. Under AIA A201 § 3.12.4, shop drawings, product data and samples are not contract documents. They show how the contractor proposes to conform to the contract documents.
Who prepares shop drawings?
The contractor, a subcontractor, or a manufacturer or supplier, for the specific project. For example, the sheet metal contractor prepares duct shop drawings and the switchboard manufacturer prepares switchboard drawings.
Should shop drawings be submitted before product data?
Usually after. Shop drawings depend on the approved sizes, weights and connection points of the products, so they are more reliable once the product data is approved.
Are coordination drawings the same as shop drawings?
Not quite. Coordination drawings combine several trades’ work to resolve conflicts. Many specs treat them as a separate submittal, and some as informational only.
Do I need shop drawings for every product?
No. The submittal articles in Part 1 of each section state which submittals are required. Many products need only product data; layouts such as ductwork and sprinkler systems and configured equipment usually need shop drawings.
What is a submittal cover sheet?
The first page of a submittal, identifying the project, spec section, submittal number and revision, the items included, the contractor’s review stamp and the deviation statement. Section 01 33 00 often prescribes its form.
Can product data be reviewed without shop drawings?
Yes. Product data is usually submitted and approved first, and shop drawings follow once sizes and connections are fixed. Reviewing shop drawings before the product is approved risks drawing the wrong equipment.
Who reviews MEP shop drawings?
The engineer of record for the discipline, usually through the architect, who checks them for conformance with the design intent. Field dimensions and coordination with other trades remain the contractor’s responsibility.
Sources
Standards and codes this page relies on. Check the edition your project and jurisdiction have adopted.
- AIA Document A201-2017, § 3.12.1 to § 3.12.4
- CSI MasterFormat, Section 01 33 00 Submittal Procedures