How to write a deviation list for an MEP submittal
What counts as a deviation, the columns a deviation list needs, how to word each entry so the engineer can act on it, and why “no deviations” is risky.
The short answer
A deviation list states, for one submittal, every place the submitted product differs from the contract documents. Each entry names the tags, where the requirement is written, what was required, what is offered, where it appears in the package and why, with room for the engineer’s action. Under AIA A201 § 3.12.8 an unlisted deviation is not approved by the stamp, so the list protects the contractor too.
- Contract basis
- AIA A201-2017 § 3.12.8, and Section 01 33 00
- Where it goes
- Cover sheet or the first pages of the submittal
- One entry per
- Difference, per tag where tags differ
- Includes
- Differences from the spec, the schedules and the drawings
What counts as a deviation
A deviation is any difference between the submitted product and what the contract documents require or show, including differences you believe are equal or better. If a reviewer reading only the documents would expect something different from what will arrive, it belongs on the list.
| Situation | Deviation? | Why |
|---|---|---|
| Named alternate manufacturer that meets every requirement | No | Allowed by the spec |
| Named alternate that is 8 inches longer than shown | Yes | Differs from the drawings |
| Higher efficiency than scheduled | List it | Better, but different; may change electrical data |
| Different refrigerant than specified | Yes | See refrigerant differs |
| Belt drive where direct drive is specified | Yes | Construction requirement in Part 2 |
| MOP higher than the design’s breaker | Yes | Affects the electrical design |
| Product not named and not allowed as equal | Not a deviation: a substitution | Follows 01 25 00 |
Step by step
Start from the review, not from memory
Use the requirement-by-requirement review of the submittal; every conflict there is a candidate. See how to review a cut sheet.
Add drawing differences
Compare dimensions, weights, connections and electrical data with the drawings, not only the spec.
Write one entry per difference
If the difference applies to several tags, list the tags in one entry; if values differ by tag, use one entry per tag.
Give the source and both values
Spec paragraph or schedule cell, specified value, submitted value and the submittal page where the submitted value appears.
State the reason and the effect
Why the product differs, such as discontinued option or lead time, and which other work it affects, such as the breaker or the pad.
Leave room for the action
A column for the engineer to mark accepted, rejected or comment, so the decision is recorded against each item.
A deviation list in practice
| No. | Tags | Requirement and source | Submitted | Page | Reason and effect |
|---|---|---|---|---|---|
| 1 | RTU-1 to RTU-4 | R-410A, 23 74 16.13 2.5.A | R-454B | 6 | R-410A no longer manufactured; adds detection and mitigation to controls |
| 2 | RTU-3 | Length 168 in., plan M-401 | 176 in. | 11 | Larger cabinet; clearance to parapet still 48 in. |
| 3 | RTU-2 | MOP 40 A, panel H1-7 | MOP 45 A | 8 | Higher-capacity fan motor; panel breaker can stay 40 A, at or below MOP |
| 4 | All | Two-year parts warranty, 2.10 | One year standard, second year extended | 14 | Extended warranty included in price |
Deviation 2, RTU-3: Plan M-401 shows a 168 in. unit length. Submitted unit is 176 in. (page 11). Clearance to the parapet is reduced from 56 in. to 48 in., which still meets the manufacturer’s minimum service clearance of 42 in.
Words that help the engineer decide
An engineer reviewing a deviation needs three things: what changed, whether it still meets the design intent, and what else it touches. Entries that answer all three are accepted faster. Entries that leave the engineer to work out the consequences tend to come back as questions, which costs a review cycle.
| Weak | Strong |
|---|---|
| Unit is slightly larger | Unit is 8 in. longer than shown on M-401; parapet clearance becomes 48 in., above the 42 in. service minimum |
| Equal refrigerant | R-454B in place of R-410A; adds factory leak detection and a fan-on mitigation sequence |
| Electrical data differs | MOP rises from 40 A to 45 A; the 40 A breaker on H1-7 remains at or below MOP and above MCA |
| Standard warranty | One-year standard warranty plus a second-year extension to meet 2.10 |
Why “no deviations” is risky
Many cover sheets carry a pre-printed statement that the submittal contains no deviations. Signing it without a check is the worst outcome for the contractor: the engineer reviews in good faith, the stamp comes back, and the undisclosed difference remains the contractor’s responsibility under § 3.12.8. If a difference is found after installation, the contractor bears the cost of the fix.
- Write “no deviations” only after the requirement-by-requirement review.
- If a value could not be checked because the cut sheet does not state it, say so; it is not a deviation, but it is not compliance either.
- Keep the list with the approved submittal. It is the record of what the engineer accepted, and buyout and closeout rely on it.
Where Cailar fits
What Cailar does
- Builds a deviation log from the conflicts and missing values found in review, each with the requirement’s source page and the submittal page, and records the reviewer’s decision on each.
- Places the deviation log in the issued package, together with review stamps that open in Bluebeam Revu.
What stays with your reviewer
- Decide which differences are acceptable or write the reason and effect for you.
- Record the architect’s final action automatically. The reviewer records it against the version reviewed.
Questions and answers
What is a deviation on a submittal?
Any difference between the submitted product and what the contract documents require or show, including differences the contractor believes are equal or better.
Why must deviations be listed in writing?
Under AIA A201 § 3.12.8 and similar contracts, the contractor is not relieved of responsibility for a deviation by the architect’s approval unless the deviation was identified in writing and specifically approved.
What should each entry on a deviation list include?
The tags, the requirement and its source, the specified value, the submitted value, the submittal page, the reason and the effect on other work, and space for the engineer’s action.
Is a substitution a deviation?
A substitution is a different product altogether and follows Section 01 25 00. Deviations are differences within a product that is otherwise allowed. A substitution request should still list its differences from the specified product.
Where does the deviation list go in the submittal?
On the cover sheet or in the first pages, before the product data, so the reviewer sees it first. Section 01 33 00 may prescribe a form or location.
Sources
Standards and codes this page relies on. Check the edition your project and jurisdiction have adopted.
- AIA Document A201-2017, § 3.12.8
- CSI MasterFormat, Section 01 33 00 Submittal Procedures