What counts as a deviation, the columns a deviation list needs, how to word each entry so the engineer can act on it, and why “no deviations” is risky.

The short answer

A deviation list states, for one submittal, every place the submitted product differs from the contract documents. Each entry names the tags, where the requirement is written, what was required, what is offered, where it appears in the package and why, with room for the engineer’s action. Under AIA A201 § 3.12.8 an unlisted deviation is not approved by the stamp, so the list protects the contractor too.

Contract basis
AIA A201-2017 § 3.12.8, and Section 01 33 00
Where it goes
Cover sheet or the first pages of the submittal
One entry per
Difference, per tag where tags differ
Includes
Differences from the spec, the schedules and the drawings

What counts as a deviation

A deviation is any difference between the submitted product and what the contract documents require or show, including differences you believe are equal or better. If a reviewer reading only the documents would expect something different from what will arrive, it belongs on the list.

Deviation or not
SituationDeviation?Why
Named alternate manufacturer that meets every requirementNoAllowed by the spec
Named alternate that is 8 inches longer than shownYesDiffers from the drawings
Higher efficiency than scheduledList itBetter, but different; may change electrical data
Different refrigerant than specifiedYesSee refrigerant differs
Belt drive where direct drive is specifiedYesConstruction requirement in Part 2
MOP higher than the design’s breakerYesAffects the electrical design
Product not named and not allowed as equalNot a deviation: a substitutionFollows 01 25 00

Step by step

  1. Start from the review, not from memory

    Use the requirement-by-requirement review of the submittal; every conflict there is a candidate. See how to review a cut sheet.

  2. Add drawing differences

    Compare dimensions, weights, connections and electrical data with the drawings, not only the spec.

  3. Write one entry per difference

    If the difference applies to several tags, list the tags in one entry; if values differ by tag, use one entry per tag.

  4. Give the source and both values

    Spec paragraph or schedule cell, specified value, submitted value and the submittal page where the submitted value appears.

  5. State the reason and the effect

    Why the product differs, such as discontinued option or lead time, and which other work it affects, such as the breaker or the pad.

  6. Leave room for the action

    A column for the engineer to mark accepted, rejected or comment, so the decision is recorded against each item.

A deviation list in practice

Deviation list for submittal 23 74 16.13-002.0 (illustrative)
No.TagsRequirement and sourceSubmittedPageReason and effect
1RTU-1 to RTU-4R-410A, 23 74 16.13 2.5.AR-454B6R-410A no longer manufactured; adds detection and mitigation to controls
2RTU-3Length 168 in., plan M-401176 in.11Larger cabinet; clearance to parapet still 48 in.
3RTU-2MOP 40 A, panel H1-7MOP 45 A8Higher-capacity fan motor; panel breaker can stay 40 A, at or below MOP
4AllTwo-year parts warranty, 2.10One year standard, second year extended14Extended warranty included in price
Entry 3 shows why the effect matters: the engineer can accept it without an electrical change because the existing breaker is still at or below the new MOP and above the MCA.
How an entry reads on its own
Deviation 2, RTU-3: Plan M-401 shows a 168 in. unit length. Submitted unit is 176 in. (page 11). Clearance to the parapet is reduced from 56 in. to 48 in., which still meets the manufacturer’s minimum service clearance of 42 in.

Words that help the engineer decide

An engineer reviewing a deviation needs three things: what changed, whether it still meets the design intent, and what else it touches. Entries that answer all three are accepted faster. Entries that leave the engineer to work out the consequences tend to come back as questions, which costs a review cycle.

Weak and strong wording
WeakStrong
Unit is slightly largerUnit is 8 in. longer than shown on M-401; parapet clearance becomes 48 in., above the 42 in. service minimum
Equal refrigerantR-454B in place of R-410A; adds factory leak detection and a fan-on mitigation sequence
Electrical data differsMOP rises from 40 A to 45 A; the 40 A breaker on H1-7 remains at or below MOP and above MCA
Standard warrantyOne-year standard warranty plus a second-year extension to meet 2.10

Why “no deviations” is risky

Many cover sheets carry a pre-printed statement that the submittal contains no deviations. Signing it without a check is the worst outcome for the contractor: the engineer reviews in good faith, the stamp comes back, and the undisclosed difference remains the contractor’s responsibility under § 3.12.8. If a difference is found after installation, the contractor bears the cost of the fix.

  • Write “no deviations” only after the requirement-by-requirement review.
  • If a value could not be checked because the cut sheet does not state it, say so; it is not a deviation, but it is not compliance either.
  • Keep the list with the approved submittal. It is the record of what the engineer accepted, and buyout and closeout rely on it.

Where Cailar fits

What Cailar does

  • Builds a deviation log from the conflicts and missing values found in review, each with the requirement’s source page and the submittal page, and records the reviewer’s decision on each.
  • Places the deviation log in the issued package, together with review stamps that open in Bluebeam Revu.

What stays with your reviewer

  • Decide which differences are acceptable or write the reason and effect for you.
  • Record the architect’s final action automatically. The reviewer records it against the version reviewed.

Questions and answers

What is a deviation on a submittal?

Any difference between the submitted product and what the contract documents require or show, including differences the contractor believes are equal or better.

Why must deviations be listed in writing?

Under AIA A201 § 3.12.8 and similar contracts, the contractor is not relieved of responsibility for a deviation by the architect’s approval unless the deviation was identified in writing and specifically approved.

What should each entry on a deviation list include?

The tags, the requirement and its source, the specified value, the submitted value, the submittal page, the reason and the effect on other work, and space for the engineer’s action.

Is a substitution a deviation?

A substitution is a different product altogether and follows Section 01 25 00. Deviations are differences within a product that is otherwise allowed. A substitution request should still list its differences from the specified product.

Where does the deviation list go in the submittal?

On the cover sheet or in the first pages, before the product data, so the reviewer sees it first. Section 01 33 00 may prescribe a form or location.

Sources

Standards and codes this page relies on. Check the edition your project and jurisdiction have adopted.