How to check the mechanical schedule against the panel schedules, tag by tag
A method for joining mechanical schedules with electrical panel schedules by tag to find voltage, phase, breaker, MCA and missing-circuit conflicts early.
The short answer
Make one table with a row per equipment tag. Fill the mechanical columns from the mechanical schedules or approved submittals (voltage, phase, horsepower or kW, MCA and MOP) and the electrical columns from the panel schedules (panel, circuit, poles, breaker, conductors, disconnect). Then check each row: voltage and phase agree, the breaker is at or below MOP and at or above MCA, conductors meet MCA, and every tag appears on both sides.
- Join key
- Equipment tag, such as RTU-2 or P-3
- Mechanical side
- Schedules on M-sheets, then approved submittals
- Electrical side
- Panel schedules and the one-line diagram
- When
- At bid, at submittal, and after every equipment approval
Why the two schedules drift apart
The mechanical engineer schedules the equipment and the electrical engineer circuits it, usually from a load list exchanged during design. Every later change, an addendum that upsizes a fan, an approved equal with a different MOP, a value-engineered heater, has to be carried across by hand. On most projects some rows do not get carried. The check below finds them before the panels and equipment are ordered.
Step by step
List every tag with power
From the mechanical, plumbing and fire protection schedules, list every tag that needs power: units, fans, pumps, heaters, controls panels, water heaters, fire pumps. Include small items such as unit heaters and condensate pumps.
Fill the mechanical columns
Voltage, phase, horsepower or kW, MCA and MOP. Use approved submittal values where they exist, and schedule values otherwise, and note which source each row uses.
Fill the electrical columns
Panel, circuit numbers, poles, breaker size and type, conductor size, disconnect type and whether the circuit is on emergency or standby power.
Check voltage and phase
Remember that nominal and nameplate voltages differ: a 460 V nameplate on a 480 V panel matches. See voltage mismatches and phase mismatches.
Check the breaker and conductors
Breaker at or below MOP and large enough to carry the load, normally at or above MCA; conductors at or above MCA. See breaker above MOP.
Find orphans
Tags on the mechanical side with no circuit, and circuits labeled with tags that no longer exist. Both are common after addenda.
Check the power source
Equipment that must run on emergency or standby power, such as smoke control fans or fire pumps, must be on the right panels.
Send the conflicts
At bid or early in construction, send them as RFIs. After approvals, send them to the electrical contractor and engineer before panels are released.
A joined table in practice
| Tag | Mechanical | Electrical | Finding |
|---|---|---|---|
| RTU-1 | 460/3/60, MCA 38 A, MOP 50 A | H1-1,3,5: 3P 50 A, 8 AWG | OK |
| RTU-2 | 460/3/60, MCA 28 A, MOP 35 A | H1-7,9,11: 3P 50 A, 8 AWG | Breaker above MOP |
| EF-4 | 208/3/60, 1.5 HP | L1-14,16: 2P 15 A | Phase: two poles for a three-phase motor |
| UH-2 | 208/1/60, 5 kW | None | No circuit |
| P-5 | None (removed by addendum 2) | H2-4,6,8: 3P 20 A | Orphan circuit |
| EF-9 smoke exhaust | 460/3/60, 10 HP | H3-12,14,16, normal power | Should be on emergency or standby |
Motors without MCA and MOP
Single motors, such as pumps and fans with separate starters, usually do not have an MCA and MOP on a nameplate. Their circuits are sized under NEC Article 430 from the full-load current in Tables 430.248 to 430.250, not from the nameplate. When the mechanical schedule gives only horsepower, check the circuit against those tables; see FLA, RLA and LRA.
- Motor
- 10 HP, 460/3/60
- NEC Table 430.250 current
- 14 A
- Conductor ampacity at 125 percent
- 17.5 A, so 12 AWG Cu at 75 °C (25 A) is enough
- Panel schedule shows
- 3P 20 A breaker, 12 AWG
- Breaker limit for an inverse time breaker, 250 percent of 14 A
- 35 A maximum, so 20 A is within it
Maximum breaker size for motor branch circuits comes from NEC Table 430.52. Motors on drives follow the drive manufacturer’s requirements as well.
When to run the check
| Pass | Using | Purpose |
|---|---|---|
| At bid or award | Design schedules on both sides | Find design conflicts and raise RFIs |
| At equipment submittal | Submittal electrical data | Catch submitted equipment that does not fit its circuit |
| After each approval | Approved data | Update panel breakers before panels are released |
Where Cailar fits
What Cailar does
- Runs a cross-trade check on the mechanical and electrical rows a reviewer supplies, joined by tag, and flags voltage conflicts, breakers above MOP and breakers below MCA, citing the sheets.
- Keeps the sheet and evidence attached to each mechanical and electrical row, so every conflict can be traced to its source.
What stays with your reviewer
- Read panel schedules from drawings automatically or assume breaker sizes. The reviewer supplies those rows.
- Size motor circuits under Article 430 or check emergency power assignments.
Questions and answers
Why do mechanical and electrical schedules disagree?
They are prepared by different engineers from a load list exchanged during design, and later changes such as addenda, bulletins and approved equals are carried across by hand. Some changes are missed on every project.
What should a mechanical-electrical coordination check include?
Voltage and phase, breaker size against MCA and MOP, conductor size against MCA, disconnects, emergency or standby power assignments, and tags that appear on only one side.
When should the schedules be compared?
At bid or award to raise RFIs, when equipment submittals arrive, and again after each approval, before panels are released for manufacture.
How are single motor circuits checked without MCA and MOP?
Using NEC Article 430: conductors from 125 percent of the full-load current in Tables 430.248 to 430.250, and the maximum breaker or fuse from Table 430.52.
What is an orphan circuit?
A circuit on a panel schedule labeled for equipment that no longer exists or was renamed, often after an addendum. It wastes a breaker space and hides missing circuits for new equipment.
Who is responsible for coordinating mechanical and electrical schedules?
The engineers of record are responsible for a coordinated design, but contractors usually carry coordination of the work under the general conditions and Division 01. In practice the mechanical and electrical contractors both benefit from running the check, because the cost of a miss lands on whoever installs first.
What tools work for this check?
A spreadsheet with one row per tag is enough for small jobs. On larger jobs, any tool that keeps the two sides joined by tag and records where each value came from saves the repeated passes after every addendum and approval.
Sources
Standards and codes this page relies on. Check the edition your project and jurisdiction have adopted.