Section 23 52 16 Condensing Boilers: efficiency at return temperature, turndown and flow

Reviewing a condensing boiler submittal: efficiency at the real return water temperature, turndown, minimum flow, venting, CSD-1 and gas pressure.

Illustration: a condensing boiler submittal where output matches but turndown is lower than specified, the boiler’s minimum flow exceeds the loop’s low-load flow, and efficiency at the design return temperature is not given.

Illustrative example

The short answer

Section 23 52 16 covers condensing boilers for hydronic heating. Check that the submittal shows input and output at the scheduled conditions, efficiency at the design return water temperature rather than only the peak rating, turndown low enough for the building’s smallest load, the boiler’s minimum flow and maximum temperature rise against the piping design, and the venting, gas pressure, condensate and control requirements.

MasterFormat division
23, HVAC
Condensing happens
When return water is below the flue gas dew point, roughly 130 °F for natural gas
Safety controls
ASME CSD-1 on most commercial boilers up to 12.5 million Btu/h input
Coordinate with
23 21 13 and 23 21 23 piping and pumps, 23 11 23 gas, 23 09 23 controls

What Section 23 52 16 covers

Condensing boilers recover the latent heat in flue gas by cooling it below its dew point, which only happens when the water returning to the boiler is cool enough. Their efficiency depends on the system as much as on the boiler. That is why a condensing boiler submittal has to be read against the heating water temperatures, the piping arrangement and the controls, not only against its rating plate. Non-condensing boilers are usually in 23 52 33 or similar sections.

Efficiency depends on return water temperature

Brochures quote peak efficiency at low return water temperature, often 95 percent or more. At a 160 °F return, the same boiler barely condenses. Ask for the manufacturer’s efficiency curve and read it at the schedule’s design return temperature, and at the lower return temperatures the reset schedule reaches in mild weather.

Illustrative efficiency against return water temperature
Return water temperatureTypical thermal efficiencyWhat is happening
80 °FAbout 97 percentStrong condensing
110 °FAbout 94 percentCondensing
130 °FAbout 89 percentNear the dew point
160 °FAbout 86 percentNot condensing
Values are illustrative. Each manufacturer publishes its own curve; use it, not this table.

Turndown and the smallest load

Turndown is the ratio of maximum to minimum firing rate. A boiler that cannot fire low enough short-cycles at light load, which wastes energy and wears the ignition system.

Worked example: is 10:1 turndown enough?
Boiler input
2,000 MBH
Minimum firing at 10:1
200 MBH
Smallest load, summer reheat
150 MBH
Minimum firing at 20:1
100 MBH
Result
10:1 cycles on and off all summer; 20:1 modulates

Multiple smaller boilers can achieve the same result. Turndown is a system property; the spec states what the engineer chose.

Flow, temperature rise and piping

  • Minimum flow: many boilers, especially low-mass watertube designs, need a minimum flow through the heat exchanger. Compare it with the lowest flow the heating loop reaches, especially in variable-primary systems.
  • Maximum temperature rise: the boiler may limit the difference between supply and return, such as 40 °F or 60 °F. A design with a 40 °F rise on a boiler limited to 30 °F is a mismatch.
  • Pressure drop through the boiler at design flow feeds the pump head; see 23 21 23 Hydronic Pumps.
  • Primary-secondary or direct piping: the installation manual states what the manufacturer allows. Check it against the piping diagram.
  • Maximum working pressure and the ASME Section IV stamp must suit the system pressure.

Input, output, altitude and redundancy

Schedules give either input or output, and the two differ by the efficiency. A boiler with 2,000 MBH input delivers about 1,900 MBH at 95 percent efficiency, and less when it is not condensing. Read which one the schedule names before comparing numbers.

  • Altitude: above a certain elevation, often 2,000 ft, burners are derated unless the boiler is certified for high altitude. Projects in Denver or Salt Lake City need the output at the site elevation.
  • Redundancy: many designs size the plant so the building can be heated with one boiler out of service, called N+1. Check the number of boilers and each one’s output against that intent, which is usually stated in the schedule notes or the basis of design.
  • Space heating plus domestic water: if the boiler also heats domestic water through an indirect tank, the schedule load includes it. The submittal should include the indirect tank or reference its own section.

Venting, gas, condensate and controls

Installation requirements to check
ItemCheck
Vent category and materialCategory IV, materials listed in the installation manual
Vent and combustion air lengthMaximum equivalent lengths against the layout
Common ventingAllowed only with the manufacturer’s approved common vent system
Gas inlet pressureMinimum and maximum against the gas design at full fire of all appliances
CondensateNeutralizer and drain to a suitable receptor
CSD-1 controlsFlame safeguard, limits and low-water cutoff as ASME CSD-1 requires
ElectricalVoltage and current for burner, controls and any integral pump
Boiler sequencingLead-lag control and interface to the building automation system
EmissionsNOx certification where an air district rule applies

Why condensing boiler submittals are returned

Common rejection reasons
ReasonHow to avoid it
Only peak efficiency shownInclude the curve and the value at design return temperature
Turndown below the specCheck the ratio for the size submitted, not the product line
Minimum flow above the loop’s low-load flowCheck the piping diagram and controls sequence
Temperature rise outside the boiler’s limitCompare the boiler limit with the scheduled supply and return
Vent length or material not shownInclude the vent table and installation manual page
CSD-1 controls missingList each required control on the submittal

Where Cailar fits

What Cailar does

  • Compares input, output, turndown and flow from the boiler data with the schedule, with MBH and GPM converted in code.
  • Marks efficiency at the design return temperature, or any other required value, as not stated when the submittal leaves it out.

What stays with your reviewer

  • Analyze the piping arrangement or controls sequence for flow or cycling problems.
  • Read efficiency off a curve or calculate seasonal efficiency.

Questions and answers

At what return water temperature does a boiler condense?

Flue gas from natural gas starts condensing when it is cooled below its dew point, around 130 °F. Return water must be below that for meaningful condensing; efficiency rises as return temperature falls.

What is boiler turndown?

The ratio of maximum to minimum firing rate. A 2,000 MBH boiler with 10:1 turndown fires down to 200 MBH; with 20:1 it fires down to 100 MBH. Higher turndown avoids short-cycling at light loads.

Does a condensing boiler need a minimum flow?

Many do, especially low-mass watertube designs. The installation manual states the minimum flow and maximum temperature rise. The heating system’s piping and controls must keep flow above that minimum.

What is ASME CSD-1?

ASME CSD-1 is the standard for controls and safety devices on automatically fired boilers, typically those up to 12.5 million Btu/h input. It covers flame safeguards, limits and low-water cutoffs. Many jurisdictions require it.

Can condensing boilers share a vent?

Only when the manufacturer allows it and supplies or approves the common vent system, because condensing boilers vent under positive pressure. Otherwise each boiler needs its own vent.

Sources

Standards and codes this page relies on. Check the edition your project and jurisdiction have adopted.