Approved equal: what “or equal” allows and what the engineer will ask you to prove
What “or approved equal” means in MEP specs, who decides equivalence, when it becomes a substitution, and how to build an equal comparison that gets approved.
The short answer
An approved equal is a product the specification does not name that the architect or engineer accepts as equivalent to the specified one. “Or approved equal” in a spec does not mean any similar product is allowed: the contractor must prove equivalence, usually with a side-by-side comparison, and the design professional decides. Depending on the specification, an equal goes through an ordinary submittal or the substitution procedure.
- Wording
- “Or approved equal”, “or equal”, “or comparable product”
- Who decides
- The architect or engineer, not the contractor or supplier
- Proof
- A point-by-point comparison with the specified product
- Procedure
- Set in 01 60 00 and 01 25 00
What “or equal” does and does not mean
Public procurement rules in many jurisdictions require specifications to allow competition, which is why “or equal” language is common. It opens the door to other products, but it puts the burden on the party proposing them. The specified product, often the basis of design, remains the standard against which equivalence is judged.
| Spec wording | Usual meaning |
|---|---|
| Manufacturer A, Model X, or approved equal | Unlisted products allowed if the engineer accepts them as equal |
| Provide one of the following: A, B, C | Only the listed manufacturers; others are substitutions |
| Basis of design A; comparable products by B or C | B and C allowed if they comply; others are substitutions |
| No substitutions | Only the named product |
When an equal becomes a substitution
Many specifications treat any unnamed product as a substitution under Section 01 25 00, with its deadlines and form, even when the paragraph says “or equal”. Others accept equals through the regular submittal with a comparison. Read both sections before deciding how to submit; an equal sent the wrong way can be returned unreviewed, and the substitution deadline may pass while it is out.
Building an equal comparison
Use the specified product’s data for the same size
Compare like with like: the same capacity, options and voltage.
Cover every requirement in the section
Go through Part 2 of the section paragraph by paragraph and give the specified and proposed values side by side.
Add the schedule values
Capacity, efficiency, airflow, flow, head, sound and electrical data for each tag.
Add the physical fit
Dimensions, weight, connections and service clearances, because the drawings were drawn around the specified product.
State every difference
Mark each value that is worse, different or not available. Hiding a difference does not make it approved; under A201 § 3.12.8 it stays the contractor’s responsibility.
| Paragraph or schedule item | Specified | Proposed | Complies |
|---|---|---|---|
| 2.3.A Casing, double wall with 2 in. insulation | Yes | Yes | Yes |
| 2.4.B Supply fan, direct drive, ECM | Yes | Belt drive | No: deviation 1 |
| Schedule: 6,000 CFM at 1.5 in. wg ESP | 6,000 CFM | 6,000 CFM | Yes |
| Schedule: MOP at 460/3/60 | 35 A | 40 A | Different: electrical to confirm |
| Dimensions L × W × H | 96 × 52 × 48 in. | 104 × 52 × 50 in. | Different: fits the space per layout |
Equals on public and federal projects
Public owners are often required to allow competition, so their specifications name a product and add “or equal”, sometimes with the salient characteristics an equal must have. On federal contracts, the Federal Acquisition Regulation clause 52.211-6, Brand Name or Equal, requires offers of equal products to show that they meet the salient physical, functional or performance characteristics listed. State and local rules vary, but the principle is the same: the owner lists what matters, and the proposer shows the equal meets it.
| Stage | How equals are usually handled |
|---|---|
| During bidding | Prior approval requests before a deadline; accepted products added by addendum |
| After award | Comparison with the submittal, or a substitution request, as the spec states |
| After a rejection | Submit the specified product; a second equal rarely gets a faster review |
Why equals are refused
- No comparison, only the proposed product’s cut sheets.
- The comparison covers headline ratings but not construction, controls or warranty requirements in Part 2.
- A key feature of the specified product is missing, such as a direct-drive fan or a stainless drain pan.
- Physical or electrical differences that would change other trades’ work are not mentioned.
- It was submitted after the substitution deadline where the spec treats equals as substitutions.
Where Cailar fits
What Cailar does
- Checks a proposed equal against the same confirmed requirements as the specified product and shows, for each one, whether the submittal meets it, conflicts or does not state it.
- Puts every accepted difference on the deviation log so the approval is recorded with the package.
What stays with your reviewer
- Decide whether a product is equal. The architect or engineer decides.
- Supply the specified product’s data if it was not uploaded.
Questions and answers
What does “or approved equal” mean?
It means a product other than the one named may be used if the architect or engineer approves it as equivalent. The contractor must show equivalence, usually with a side-by-side comparison against the specified product.
Who decides whether a product is equal?
The architect or engineer of record. Suppliers and contractors propose; the design professional decides, usually in writing on the submittal or substitution response.
Is an approved equal the same as a substitution?
It depends on the specification. Some projects accept equals through ordinary submittals with a comparison; others treat any unnamed product as a substitution under Section 01 25 00, with its own deadline and form.
What should an approved equal submittal include?
A paragraph-by-paragraph comparison with the specified product, the schedule values, physical dimensions, weight, connections and electrical data, with every difference stated.
Can the engineer reject an equal that meets the scheduled ratings?
Yes. Equivalence covers every requirement in the specification and the fit with the design, not only scheduled ratings. A product that matches capacity but not construction, controls or size can be rejected.
How long does the engineer take to review an equal?
The review period in Section 01 33 00 or 01 25 00 applies, and equals often take longer because the engineer compares two products and may consult other disciplines. Submit equals early, especially for long-lead equipment, and include a complete comparison so the first review is the last.
Does approval of an equal change the contract price?
Not by itself. Unless the owner asks for a credit or the contract says otherwise, the contract sum stays the same and the contractor keeps any saving or absorbs any extra cost, including changes to other work the equal causes.
Sources
Standards and codes this page relies on. Check the edition your project and jurisdiction have adopted.
- CSI MasterFormat, Sections 01 25 00 and 01 60 00
- AIA Document A201-2017, § 3.4.2 and § 3.12.8
