Basis of design: what it means in a spec and what it obliges an alternate to match
What a basis-of-design product is, how it differs from a named alternate, why alternates must match more than the scheduled ratings, and how to compare them.
The short answer
The basis of design is the specific product the engineer used to design the system, named in the specification and usually reflected in the schedules, dimensions, weights and electrical data on the drawings. Other named manufacturers may be allowed, but the design around the equipment was drawn for the basis-of-design product. An alternate must meet the scheduled performance and fit the space, structure, connections and electrical design, or the contractor carries the cost of the differences.
- Defined in
- Section 01 60 00 Product Requirements, or the general conditions
- Also called
- BOD, or basis-of-design product
- Drawn around it
- Dimensions, weights, clearances, connections, electrical data
- Alternates
- Named manufacturers, or approved equals, that must match it
How specs use the term
Specifications typically name the basis of design in a paragraph such as “Basis-of-Design Product: Subject to compliance with requirements, provide Manufacturer A, Model X, or comparable product by one of the following.” The phrase sets the standard of quality and performance. The listed alternates are allowed only if they meet every requirement of the section and the drawings.
| Term | Meaning | Path |
|---|---|---|
| Basis of design | The product the engineer designed around | Ordinary submittal |
| Named alternate or comparable product | Other listed manufacturers allowed if they comply | Ordinary submittal with a comparison where the spec asks |
| Approved equal | An unlisted product the engineer may accept as equivalent | Depends on the spec; often a comparison or substitution request |
| Substitution | Anything not named | Section 01 25 00 |
What the design assumes about the basis of design
The engineer does not only use the basis-of-design product for its rated capacity. Its physical and electrical characteristics are built into the drawings, usually without being stated as requirements.
| Assumption | Where it shows on the drawings | If the alternate differs |
|---|---|---|
| Footprint and height | Plans, sections, mechanical room layouts | Clearances, access and code working space may fail |
| Operating weight | Structural framing and pads | Structural review and possible reinforcement |
| Connection locations and sizes | Piping and duct layouts | Rerouting, extra fittings, pressure drop |
| Electrical data | Panel schedules, feeders | Breaker and wire changes; see MCA and MOP |
| Sound | Acoustic design and room criteria | Added attenuation |
| Controls points | Points list and sequences | Programming changes and extra points |
| Service clearance | Plans | Service panels blocked by walls or other equipment |
Comparing an alternate with the basis of design
Collect both data sets
Get the basis-of-design product data for the same size and options, from the manufacturer’s site or the engineer, alongside the alternate’s submittal.
Compare the scheduled values
Capacity, efficiency, airflow, static pressure, flow, head and other scheduled values for each tag.
Compare the hidden assumptions
Dimensions, weight, connection sizes and locations, electrical data and sound, from the table above.
List every difference
Each difference that affects other work is a deviation to identify under 01 33 00, with the trade it affects.
- Capacity at design conditions
- Basis 200 tons · alternate 200 tons
- Full-load efficiency
- Basis 10.2 EER · alternate 10.4 EER
- Length
- Basis 18 ft 4 in. · alternate 21 ft 9 in.
- Operating weight
- Basis 14,800 lb · alternate 16,900 lb
- MOP at 460 V
- Basis 350 A · alternate 400 A
On performance the alternate is equal or better. On the drawings, it no longer fits the screened yard, needs a structural check and a larger feeder breaker. Those differences are the contractor’s to resolve unless the engineer accepts them. Values are illustrative.
Reading basis of design on the drawings
Schedules often carry the basis of design in a column or a note, such as “Basis of design: Manufacturer A, Model X” or simply a manufacturer and model in the equipment column. Some schedules list performance only and leave the product to the specification. Where both name a product and they disagree, raise an RFI; the specification usually governs under the order of precedence in the contract, but the engineer should confirm.
- Model numbers on schedules are often partial; the options that matter may be in the spec rather than in the model string.
- Dimensions on plans are usually drawn from the basis-of-design product’s data at the time of design, which may be older than the current catalog.
- Performance specifications describe the result without naming a product. There is no basis of design to compare with, so the submittal is checked against the criteria alone.
Who pays for the differences
Most specifications make the contractor responsible for the cost of changes to other work caused by using a product other than the basis of design, including redesign, structural review and other trades’ changes. The wording is usually in Section 01 60 00 or in the product options paragraph. That is why the comparison should be done before the alternate is priced, not after it is approved.
Where Cailar fits
What Cailar does
- Checks a submitted product against the same confirmed requirements whether it is the basis of design or an alternate, with every value tied to its page.
- Records each difference the reviewer accepts on the deviation log in the issued package.
What stays with your reviewer
- Hold basis-of-design product data that was not uploaded, or compare dimensions and connection locations against the drawings.
- Decide whether an alternate is acceptable.
Questions and answers
What does basis of design mean in a specification?
It is the specific manufacturer and model the engineer used to design the system. It sets the standard of quality and performance, and the drawings are drawn around its size, weight, connections and electrical data.
Can I submit a manufacturer other than the basis of design?
If the specification lists it as an acceptable manufacturer or comparable product, yes, as an ordinary submittal, provided it meets every requirement. Unlisted products follow the approved-equal or substitution rules in the spec.
Who pays if an alternate needs a bigger pad or breaker?
Under most specifications, the contractor who chose the alternate pays for changes to other work it causes, including redesign and other trades’ changes. Check Section 01 60 00 and the product options paragraph.
Is the basis of design the same as sole source?
No. Sole source means only one product is allowed. A basis-of-design product is the reference, and other listed or approved products may be used if they comply.
What should a basis-of-design comparison include?
The scheduled performance values plus the physical and electrical characteristics the drawings rely on: dimensions, weight, connection sizes and locations, electrical data, sound and controls points.
Is the basis-of-design product always the best choice?
Not always, but it is the lowest-risk choice for coordination, because the drawings were drawn around it. An alternate can be cheaper or faster and still cost more once structural, electrical and layout changes are counted.
Sources
Standards and codes this page relies on. Check the edition your project and jurisdiction have adopted.
- CSI MasterFormat, Section 01 60 00 Product Requirements
- AIA Document A201-2017, General Conditions of the Contract for Construction