Delegated design: when the contractor’s engineer designs part of the MEP work
What delegated design means under AIA A201 § 3.12.10, the MEP work it usually covers, what a sealed submittal must contain, and what it costs in time.
The short answer
Delegated design is design work the contract documents assign to the contractor, to be done by a licensed design professional the contractor hires, within performance and design criteria the architect or engineer sets. Common MEP examples are seismic restraint of equipment and piping, fire sprinkler hydraulic design, and some pipe supports and hangers. The submittal must be signed and sealed, and it takes longer to prepare and review than an ordinary product submittal.
- Contract basis
- AIA A201-2017 § 3.12.10, or similar general conditions
- Who designs
- A licensed professional engineer retained by the contractor or a subcontractor
- Who sets the criteria
- The architect or engineer of record
- Building code term
- Often a deferred submittal under the IBC
How delegated design works
Under AIA A201 § 3.12.10, the contractor is not required to provide professional design services unless the contract documents specifically require them. When they do, the architect specifies the performance and design criteria the services must satisfy, and the contractor’s design professional signs and seals the drawings, calculations and certifications. The architect reviews them for conformance with the design concept and the criteria, and may rely on the sealed work.
| Party | Responsibility |
|---|---|
| Engineer of record | Sets performance and design criteria; reviews for conformance with the design concept |
| Contractor | Retains the delegated engineer, coordinates the work, submits the sealed documents |
| Delegated engineer | Designs the delegated portion and seals it, usually licensed in the project’s state |
| Building official | May require the delegated design as a deferred submittal before that work is installed |
Where MEP projects use it
| Item | Usual section | What the delegated engineer produces |
|---|---|---|
| Seismic restraint of equipment, piping and duct | 23 05 48, 22 05 48, 26 05 48 | Restraint layouts, anchorage calculations, certification of equipment |
| Fire sprinkler system design | 21 13 13 and related | Layout, hydraulic calculations to NFPA 13, sometimes sealed per local rules |
| Vibration isolation selection | 23 05 48 | Isolator selections and deflections, sometimes combined with seismic |
| Pipe supports for large or high-temperature piping | 23 05 29 | Support and anchor design, expansion calculations |
| Equipment support frames and dunnage | Structural or mechanical sections | Frame design for rooftop equipment |
Worked example: the seismic force on a rooftop chiller
- Operating weight Wp
- 16,900 lb
- SDS, ap, Rp, Ip
- 1.0, 1.0, 2.5, 1.5
- Height factor at the roof, 1 + 2z/h
- 3.0
- Fp = 0.4 × ap × SDS × Wp ÷ (Rp ÷ Ip) × (1 + 2z/h)
- 0.4 × 16,900 ÷ 1.667 × 3.0 = 12,170 lb
- Check against minimum and maximum
- Between 7,605 lb and 40,560 lb, so 12,170 lb governs
This is why delegated seismic design cannot be done until the equipment is approved: the weight and the manufacturer’s certification feed the calculation. ASCE 7-22 revised this equation; use the edition the building code adopted.
What a delegated design submittal must contain
- Drawings and calculations signed and sealed by a professional engineer, licensed where the project requires.
- A statement of the performance and design criteria used, matching those in the contract documents.
- The equipment data the design relies on, from the approved product submittals.
- For seismic work, the manufacturer’s certification where the code requires certified equipment, and the anchorage details for each piece.
- A certification that the design complies with the criteria, if the spec asks for one.
Coordinating delegated design with product submittals
Name the delegated engineer early
Many specifications require the delegated engineer’s qualifications to be submitted first. Getting that approved early avoids a second wait later.
Feed approved data, not catalog data
Send the delegated engineer the approved submittals for the equipment involved, with weights, dimensions and anchorage points. Catalog figures from the bid may be for another size or option.
Resubmit when the inputs change
If an equipment submittal is revised, for example to a heavier alternate, the delegated design that used it may need to be revised and resubmitted too.
Coordinate with the structure
Anchorage and support loads go to the structural engineer of record, who confirms the building can take them. Large rooftop or suspended equipment is where this matters most.
Schedule and cost
Delegated design waits on product approval, because it needs the actual weights, dimensions and data. It then needs the delegated engineer’s time, the engineer of record’s review, and sometimes the building official’s review as a deferred submittal. Put delegated design items on the submittal register with their own dates, after the product submittals they depend on, and allow for the longer review periods many projects set in 01 33 00.
Where Cailar fits
What Cailar does
- Reads weights and other values from approved product submittals with their pages, so the data a delegated engineer relies on is traceable.
- Shows the page behind each value, so a reviewer can confirm the delegated engineer used the approved data and not an earlier catalog figure.
What stays with your reviewer
- Perform seismic, hydraulic or structural design, or seal anything.
- Review delegated design calculations.
Questions and answers
What is delegated design in construction?
Design work that the contract documents assign to the contractor, performed by a licensed design professional the contractor retains, within performance and design criteria set by the architect or engineer of record.
Who is responsible for a delegated design?
The delegated design professional who seals it is responsible for the design. The architect or engineer of record sets the criteria and reviews the submittal for conformance with them and with the design concept.
What MEP work is commonly delegated?
Seismic restraint of equipment and distribution systems, fire sprinkler layout and hydraulic calculations, vibration isolation selection, and supports for large or high-temperature piping.
What is a deferred submittal?
A building code term for portions of the design submitted to the building official after the permit is issued, often delegated design items such as fire sprinklers or seismic restraints. They must be approved before that work is installed.
Does the delegated engineer need a license in the project’s state?
Usually yes. Most jurisdictions require sealed engineering documents to be prepared by an engineer licensed in that state. The specification and the building official confirm the requirement.
Does the engineer of record approve a delegated design?
The engineer of record reviews it for conformance with the performance and design criteria and the design concept, and returns it with an action. Responsibility for the design itself stays with the delegated engineer who sealed it.
Can a manufacturer provide the delegated design?
Often, yes. Seismic restraint and vibration isolation manufacturers commonly provide sealed designs for their products through their own licensed engineers, which the contractor then submits. The spec may set qualifications the engineer must meet.
Sources
Standards and codes this page relies on. Check the edition your project and jurisdiction have adopted.
